The House Truth

The House Truth Field Notes

The 5 A.M. Executive Portfolio Report

By Ben Vinson (Bennett Vinson)

The 5 a.m. executive report rolls up every active property that has yet to reach confirmed lease-ready. Leadership starts with the portfolio and market totals, then expands a market and opens an individual property when it needs to see what is driving the delay.

Illustrative sample. All 96 properties, dates, amounts, and action owners below are fictional. Snapshot date: November 10, 2026.

Portfolio and market recap

Active properties and estimated rent exposure
MarketActiveAhead or on trackForecast lateExposure to dateAdditional forecastProjected total
Portfolio total967224$7,650$12,310$19,960
Atlanta543915$4,950$7,530$12,480
Phoenix42339$2,700$4,780$7,480

Atlanta has the largest projected exposure at $12,480. Open either market below to see its active properties, ordered by projected exposure.

Expand a market to see its projects

Atlanta · 54 active · 15 forecast late · $12,480 projected exposure
  • Atlanta 01 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Atlanta 02 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Atlanta 03 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Atlanta 04 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Available scope is moving below the preferred pace. Source team: Construction. Next action owner: Assigned contractor. Due: 2026-11-10. Confirm remaining work and recovery date. Evidence to clear: Verified progress against the scope.

  • Atlanta 05 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Atlanta 06 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Atlanta 07 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Atlanta 08 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Available scope is moving below the preferred pace. Source team: Construction. Next action owner: Assigned contractor. Due: 2026-11-10. Confirm remaining work and recovery date. Evidence to clear: Verified progress against the scope.

  • Atlanta 09 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Atlanta 10 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Atlanta 11 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Atlanta 12 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Available scope is moving below the preferred pace. Source team: Construction. Next action owner: Assigned contractor. Due: 2026-11-10. Confirm remaining work and recovery date. Evidence to clear: Verified progress against the scope.

  • Atlanta 13 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Atlanta 14 · Forecast late · $720 projected exposure

    Target 2026-11-07 · Projected 2026-11-15 · Daily rent $90 · Exposure to date $270 · Additional forecast $450.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Atlanta 15 · Forecast late · $60 projected exposure

    Target 2026-11-11 · Projected 2026-11-12 · Daily rent $60 · Exposure to date $0 · Additional forecast $60.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Atlanta 16 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 17 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 18 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 19 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 20 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 21 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 22 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 23 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 24 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 25 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 26 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 27 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 28 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 29 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 30 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 31 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 32 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 33 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 34 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 35 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 36 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 37 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 38 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 39 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 40 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 41 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 42 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 43 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 44 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 45 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 46 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 47 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 48 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 49 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 50 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 51 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 52 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 53 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Atlanta 54 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

Phoenix · 42 active · 9 forecast late · $7,480 projected exposure
  • Phoenix 01 · Forecast late · $990 projected exposure

    Target 2026-11-06 · Projected 2026-11-17 · Daily rent $90 · Exposure to date $360 · Additional forecast $630.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Phoenix 02 · Forecast late · $990 projected exposure

    Target 2026-11-06 · Projected 2026-11-17 · Daily rent $90 · Exposure to date $360 · Additional forecast $630.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Phoenix 03 · Forecast late · $990 projected exposure

    Target 2026-11-06 · Projected 2026-11-17 · Daily rent $90 · Exposure to date $360 · Additional forecast $630.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Phoenix 04 · Forecast late · $990 projected exposure

    Target 2026-11-06 · Projected 2026-11-17 · Daily rent $90 · Exposure to date $360 · Additional forecast $630.

    Gap driving the forecast: Available scope is moving below the preferred pace. Source team: Construction. Next action owner: Assigned contractor. Due: 2026-11-10. Confirm remaining work and recovery date. Evidence to clear: Verified progress against the scope.

  • Phoenix 05 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Phoenix 06 · Forecast late · $900 projected exposure

    Target 2026-11-06 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $360 · Additional forecast $540.

    Gap driving the forecast: Water activation instructions missing from the purchase file. Source team: Closing. Next action owner: Assigned utility action owner. Due: 2026-11-10. Confirm the provider and activation appointment. Evidence to clear: Activation confirmation.

  • Phoenix 07 · Forecast late · $810 projected exposure

    Target 2026-11-07 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $270 · Additional forecast $540.

    Gap driving the forecast: Existing permit status missing from the purchase file. Source team: Closing. Next action owner: Assigned permit action owner. Due: 2026-11-10. Confirm the remaining sign-off and schedule the visit. Evidence to clear: Authority’s final sign-off.

  • Phoenix 08 · Forecast late · $810 projected exposure

    Target 2026-11-07 · Projected 2026-11-16 · Daily rent $90 · Exposure to date $270 · Additional forecast $540.

    Gap driving the forecast: Available scope is moving below the preferred pace. Source team: Construction. Next action owner: Assigned contractor. Due: 2026-11-10. Confirm remaining work and recovery date. Evidence to clear: Verified progress against the scope.

  • Phoenix 09 · Forecast late · $100 projected exposure

    Target 2026-11-11 · Projected 2026-11-12 · Daily rent $100 · Exposure to date $0 · Additional forecast $100.

    Gap driving the forecast: HOA exterior approval details missing from the purchase file. Source team: Closing. Next action owner: Assigned HOA action owner. Due: 2026-11-10. Confirm the submission deadline and earliest decision date. Evidence to clear: Written HOA decision.

  • Phoenix 10 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 11 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 12 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 13 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 14 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 15 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 16 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 17 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 18 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 19 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 20 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 21 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 22 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 23 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 24 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 25 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 26 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 27 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 28 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 29 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 30 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 31 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 32 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 33 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 34 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 35 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 36 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 37 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 38 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 39 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 40 · Ahead · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-10 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 41 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

  • Phoenix 42 · On track · $0 projected exposure

    Target 2026-11-11 · Projected 2026-11-11 · Daily rent $90 · Exposure to date $0 · Additional forecast $0.

    No open delay is driving the forecast in this sample.

Show where each gap started and who clears it

For purchases, Closing owns capturing HOA, utility, and permit details in the closing documents and handing each next action to a named owner. The project view keeps the source team and current action owner visible. List every open gap, flag which one drives the forecast, and count each delayed property-day once in the portfolio total. The clock stops at confirmed lease-ready.

See the 5 A.M. Report for SFR Renovations for the daily operating view.

Use the Purchase Closing Handoff Checklist to capture these details before renovation starts.

in X f @